West Yorkshire Police and West Yorkshire Police Authority’s plans for two new Divisional Headquarters and a specialist operational training facility are underway.
In June 2010 the Home Office granted permission for West Yorkshire Police to continue with these PFI projects and others by endorsing the allocation of £216 million of credits to the PFI Programme and Estates Strategy.
Here are the details of each of the main individual projects plus ways you can comment on the proposals, or join a mailing list to receive future updates.
- Key Milestones
- Chief Constable's Vision of the Future
- The Scheme & Facility Management (FM) Services Required
- New Divisional HQ for Wakefield
- New Divisional HQ for City and Holbeck
- New Specialist Operational Training Facilites, Wakefield
- Latest Updates
- Public Consultation Events
- Trade Enquiries
- Frequently Asked Questions
- Have Your Say / Keep Up to Date
Key Milestones
| Milestones | Date |
| ISDS submissions to WYP | 11th March 2011 |
| Bidders Informed of decision week commencing | 25th April 2011 |
| ISRS issued | 3rd May 2011 |
| ISRS submissions to WYP | 28th June 2011 |
| Pre preferred bidder Final Business Case (FBC) submitted to Home Office | 14th July 2011 |
| Approval of pre preferred FBC | 10th August 2011 |
| Intention to Submit Final Tenders (ISFT) issued | 11th August 2011 |
| Final Tenders submitted | 26th September 2011 |
| Preferred bidder appointed subject to Home Office and Treasury approval | W/c 14th December 2011 |
| Alcatel Period | Dec 2011 - Jan 2012 |
| Detailed Planning Application submitted | End Dec 2011 |
| Preferred Bidder Final Business Case submitted | 20th October 2011 |
| Planning Permission gained | April 2012 |
| Approval of Final Business Case | March 2012 |
| Judicial Review Period expires | May 2012 |
| Financial Close | May 2012 |
| Building Period Commences | June 2012 |
| Buildings Become Operational | June 2014 |
Chief Constable's Vision of the Future
"The local neighbourhoods will be placed at the forefront of our service delivery, with specialist and support services underpinning these to provide an effective and efficient service infrastructure."
The Scheme & Facility Management (FM) Services Required
The Scheme
- Police operational and training accommodation Private Finance Initiative contract for around 25 to 30 years (including works)
- The scheme is for the design, build, finance, operation and
management of new facilities, together with the associated
services and support functions - New Divisional Headquarters building with an associated
custody facility, for the City & Holbeck (South Leeds) Division - New Divisional Headquarters building with an associated
custody facility, for the Wakefield Division - New centralised Specialist Operational Training Facility at our
existing Carr Gate site, Wakefield
FM Services Required
The following FM services are currently proposed to be included within the contracts:
- Planned, Cyclical and Reactive Maintenance
(premises and plant) - Life cycling of plant and equipment
- Provision of furniture
(Office furniture, storage and display equipment) - Grounds maintenance
- Pest control services
- Sanitary vending
- Security services
(Carr Gate and Operational Support Site) - Cleaning services
(Including custody areas) - Energy management
Full details of services required will be included in the Output Specification
New Divisional HQ for Wakefield
Click here to view map and area photo of the planned site. (PDF 1.87mb)
Facilities
Total internal gross floor area of approximately 11,500m2, including:
- Office Accommodation
- A 35 cell custody suite.
- Parking facilities for approximately 409 vehicles including:
- Operational vehicles
- Staff vehicles including accessible spaces
- Visitors vehicles including accessible bays
Other external facilities to include:
- Refuse Compound
- Fuel Tank/Pump
New Divisional HQ for City and Holbeck
Click here to view map and area photo of the planned site. (PDF 2.26mb)
Facilities
Total internal gross floor area of approximately 12,500m2, including:
- Office accommodation
- A 40 cell custody suite
Parking facilities for approximately 416 vehicles including:
- Operational vehicles
- Staff vehicles including accessible bays
- Visitors vehicles including accessible bays
Other external facilities to include:
- Refuse compound
- Fuel tank/pump/bunkered fuel
New Specialist Operational Training Facilites, Wakefield
Click here to view map and area photo of the planned site. (PDF 4.3mb)
Facilities
Total buildings area of approximately 20,000m2, including:
- Training hub including -
reception, classrooms, 3 gyms, storage and offices, etc. - Public order training facilities including -
storage areas, breakout areas, large briefing room, classroom, training arena, etc. - Driver training unit block
- Firearms training block including -
100m (x1) and 50m (x2) firing ranges, armoury, etc. - Method of entry area (approximately 400m2)
- Sub-station and generator buildings
- Gatehouse
External facilities to include:
- Parking for approximately 425 staff and operational vehicles
- including 2 secure compounds for approximately 55 vehicles
- Car wash/fuel area
- Dog training area
Latest Updates
18th May 2012
Interserve, the preferred tenderer, have indicated that they would like to access the Elland Road, Leeds site on Tuesday, 22nd May 2012.
They will be conducting some Site Investigation Surveys over two days and will be drilling boreholes on the car park retaining wall line at the top of the bank in the south west corner.
This means that a small amount of drilling machinery etc will be moved onto the site but this is NOT the start of construction works, this is scheduled to commence sometime in June.
27th March 2012
West Yorkshire Police Preferred Bidder joint release
West Yorkshire Police Authority and West Yorkshire Police have appointed a consortium led by Interserve and Equitix as Preferred Bidder to design, build, finance and service two new divisional headquarters (DHQs), custody suites and a specialist operational training facility.
Preferred Bidder status means the Interserve / Equitix consortium has formally signed up to a number of commitments to work together with West Yorkshire Police to reach financial close (the point at which the contract is signed) in May 2012.
The new divisional headquarters and custody facilities will be located at Elland Road in Leeds (within the City and Holbeck Division) and Havertop Lane at Normanton (within the Wakefield Division). These facilities will provide a modern, flexible working environment and importantly, support West Yorkshire Police’s drive to modernise services that are provided to local communities.
The new Specialist Operational training centre will be located next to the Force’s Operational Support Division at Carr Gate in Wakefield and will include state of the art firearms training ranges, public order and driver training facilities.
The Planning application for the Elland Road scheme has been approved subject to the decision notice being issued. The Planning application decisions for the Havertop Lane and the Carr Gate facilities will be known in the next few weeks.
Subject to the successful outcome of the planning applications, construction work will start on each of the sites in June 2012, to be completed in 2014. The consortium will then be responsible for the delivery of facilities management services (including cleaning, maintenance and energy management) once the buildings are completed.
Chair of West Yorkshire Police Authority, Councillor Mark Burns-Williamson, said: “I am delighted to confirm the formal appointment of the Interserve / Equitix consortium as preferred bidder following a detailed and competitive bidding process. Throughout the development of the proposals the consortium have demonstrated commitment, vision and a proven ability to deliver innovative facilities on time, on budget.”
Vice Chair of West Yorkshire Police Authority, Councillor Les Carter said: “An allocation of PFI Credits will be made by the Home Office to meet the capital cost of over £100million in order to deliver these vital facilities which will enable the force to modernise and improve the services it delivers to the public. This investment will have a tremendously positive impact on the communities we serve, both through improvements in service delivery, and in the form of employment and training opportunities for local people resulting from the construction process.”
Nigel Brook Assistant Chief Officer (Finance and Business Services) said: “In January the project was subject to a Gateway 3 review undertaken by National Policing Improvement Agency and Local Partnerships. I am pleased to report that this resulted in a positive outcome, with the project being awarded a rare ‘green’ rating. This provides reassurance to all of our partners that we are in an excellent position to reach financial close and commence the construction process in the Summer”.
_________________________________________________________________________________________________________________________________
27th February 2012
Early works to trees and vegetation at Carr Gate, Wakefield site (PDF)
Early works to trees and vegetation at City & Holbeck development site (PDF)
14th December 2011
Go-Ahead for West Yorkshire Police PFI Project
20th September 2011
PFI Scheme Calls for Final Tender
21st July 2011
Elland Road Site – Temporary fence
Further details of the boundary line can be found on the attached drawing PDF document.
Please click on the below to view archived updates
__________________________________________________________________________________________________________________________
Public Consultation Events
Leeds DHQ - Elland Road development
Leeds DHQ Community Consultation 2 Mar 2011 (PDF)
You asked...We said ..Consultation Feedback (PDF)
Leeds DHQ Community Consultation 6 Jul 2011 (PDF)
You asked...We said...Consultation Feedback (PDF)
Leeds DHQ Community Consultation 23 Nov 2011 (PDF)
You asked...We said..Consultation Feedback (PDF)
Leeds DHQ Community Consultation 30 Jan 2012 (PDF)
You asked ..We said ..Consultation Feedback (PDF)
Leeds DHQ Community Consultation 5 Mar 2012
Please click here to view the Leeds Planning Application and search for reference 12/00241/RM
You asked...We said...Consultation Feedback (PDF)
Wakefield DHQ - Havertop Lane development
Wakefield DHQ Community Consultation 20 Dec 2010 (PDF)
You asked...We said...Consultation Feedback (PDF)
Wakefield DHQ Community Consultation 13 Jul 2011
You asked...We said..Consultation Feedback (PDF)
Wakefield DHQ Community Consultation 7 Dec 2011PDF)
You asked..We said ..Consultation Feedback (PDF)
Wakefield DHQ Community Consultation 31 Jan 2012 (PDF)
You asked ..We said ...Consultation Feedback (PDF)
Wakefield DHQ Community Consultation 12 Mar 2012
Please click here to view the Wakefield Planning Application and search for reference 12/00199/FUL
You asked...We said...Consultation Feedback (PDF)
Carr Gate, Wakefield - Specialist Operations Training
Carr Gate Specialist Ops Training Facility Public Consultation 21 Dec 2010
You asked..We said...Consultation Feedback (PDF)
Carr Gate Specialist Ops Training Facility Public Consultation 20 Jul 2011
You asked...We said..Consultation Feedback (PDF)
Carr Gate Specialist Ops Training Facility Public Consultation 29 Nov 2011 (PDF)
You asked...We said ...Consultation Feedback (PDF)
Carr Gate Specialist Ops Training Facility Public Consultation 23 Jan 2012 (PDF)
You asked ..We said ..Consultation Feedback (PDF)
Carr Gate Specialist Ops Training Facility Public Consultation 7 Mar 2012
Please click here to view the Wakefield Planning Application and search for reference 12/00196/FUL
You asked...We said...Consultation Feedback (PDF)
Trade Enquiries
The successful tenderer has indicated that any and all trade enquiries can be made directly to them via the following email address.
Interserve
Frequently Asked Questions
Have Your Say / Keep Up to Date
A community consultation programme is underway to ensure that local people are aware of the plans and are kept fully up to date with the progression, and to also gain the views of local people. A number of events have been held and more are planned.
In the meantime, please use the link below to send in your feedback. You can also join a mailing list to keep in touch with how the projects are progressing by adding your email address to the form.
Please click here to have your say/send your feedback
You can also keep updated on changes to this page via 'RSS' by clicking here
Alternatively subscribe to updates to this page by email
Note the above RSS feed / email alert system uses third party websites to generate an RSS feed of this page and email subscription tool. West Yorkshire Police are not responsible for these third party sites, their accuracy or the frequency of their updates.
DISCLAIMER: West Yorkshire Police do not accept any responsibility for the content of any external websites.
For non-emergencies dial 101
In an emergency always dial 999